17
Sun, Nov
52 New Articles

Legislative Changes Supporting the Restart of Wind Power Development

Hungary
Tools
Typography
  • Smaller Small Medium Big Bigger
  • Default Helvetica Segoe Georgia Times

Since the beginning of the year, the Government has modified the previous legal environment concerning the development of wind power plants in several areas to increase wind power capacity. According to the Ministry of Energy's communication so far, wind power capacity is expected to increase to around 1,000 MW by 2030.

The main changes are summarised below:

Main changes to building regulations 

  1. Protection distance: the protection zone is reduced from the previous distance of 12 km to 700 m, thus significantly increasing the extent of areas that can be considered for wind farm development, subject to the zoning restrictions, outside building areas in special zones exclusively for agricultural or renewable energy purposes. Within building areas or protection zones, wind farms may be installed only in industrial economic zones where the investment is of major economic importance, so that large energy consumers can meet their own energy needs (in addition to solar power) with wind farms, thus allowing a more balanced renewable energy portfolio.
  2. Facilitated area: areas designated by the Minister responsible for energy policy, which are particularly favourable for wind energy utilisation, can be developed in which environmental or building permits can be obtained under simplified conditions and in an accelerated procedure (50 days).
  3. Height limit: the previous objective height limit of 100 metres for wind turbines has also been removed, leaving the more flexible general rule that the height of wind turbines is limited only to the extent that they would interfere with air traffic or the operation of telecommunications, communications, and defence networks.
  4. Owners' consent: the previous rule requiring consent from owners of neighbouring properties within 1 km of wind farms has also been abolished.

Main changes to the technical rules

Some technical restrictions on wind farm development before 2024, such as a maximum generating unit capacity of 2MW, a maximum peripheral (blade speed) of 60 m/s and a maximum noise level of 60 decibels (40 decibels outside the safety zone), have also been removed. The objective limit of 50 m on the length of a wind turbine blade has also been removed, leaving the restriction that the length of the wind turbine blade must be such that it does not approach the ground surface more than twice the size of the roadway clearance during operation.

Main changes to authorisation rules

Finally, the previous limitation on the number of official permits that can be issued for the construction and commissioning of wind farms and the capacity of wind farms that can be authorised, as well as the obligation to submit tenders, will be removed. The lifting of these restrictions will also significantly facilitate the restart of future wind power projects.

By Gabor Simon, Partner, Head of Energy and Procurement, and Kristof Szeredi, Senior Associate, Finance, Projects and Restructuring, DLA Piper Hungary

Hungary Knowledge Partner

Nagy és Trócsányi was founded in 1991, turned into limited professional partnership (in Hungarian: ügyvédi iroda) in 1992, with the aim of offering sophisticated legal services. The firm continues to seek excellence in a comprehensive and modern practice, which spans international commercial and business law. 

The firm’s lawyers provide clients with advice and representation in an active, thoughtful and ethical manner, with a real understanding of clients‘ business needs and the markets in which they operate.

The firm is one of the largest home-grown independent law firms in Hungary. Currently Nagy és Trócsányi has 26 lawyers out of which there are 8 active partners. All partners are equity partners.

Nagy és Trócsányi is a legal entity and registered with the Budapest Bar Association. All lawyers of the Budapest office are either members of, or registered as clerks with, the Budapest Bar Association. Several of the firm’s lawyers are admitted attorneys or registered as legal consultants in New York.

The firm advises a broad range of clients, including numerous multinational corporations. 

Our activity focuses on the following practice areas: M&A, company law, litigation and dispute resolution, real estate law, banking and finance, project financing, insolvency and restructuring, venture capital investment, taxation, competition, utilities, energy, media and telecommunication.

Nagy és Trócsányi is the exclusive member firm in Hungary for Lex Mundi – the world’s leading network of independent law firms with in-depth experience in 100+countries worldwide.

The firm advises a broad range of clients, including numerous multinational corporations. Among our key clients are: OTP Bank, Sberbank, Erste Bank, Scania, KS ORKA, Mannvit, DAF Trucks, Booking.com, Museum of Fine Arts of Budapest, Hungarian Post Pte Ltd, Hiventures, Strabag, CPI Hungary, Givaudan, Marks & Spencer, CBA.

Firm's website.

Our Latest Issue