Automatic Extension of the Validity of Building Permits and Town Planning Certificates During the State of Alert

Romania
Tools
Typography
  • Smaller Small Medium Big Bigger
  • Default Helvetica Segoe Georgia Times

The state of alert that followed the state of emergency has been extended several times during the last year and a half by Government Decisions. Some of these decisions were annulled by the competent courts (even if the court rulings are not final). Also, there are ongoing litigation proceedings aiming at challenging the legality of such Government Decisions. In this context, one would legitimately ask: what effect would have the annulment of the Government Decisions extending the state of alert on the validity of the building permits and town planning certificates which were prolonged during the state of alert?

During the state of emergency, the validity of the documents issued by the authorities was automatically extended for the entire duration of the state of emergency. Moreover, the regulations adopted during the state of alert provided for the prolongation of the validity of such documents with an additional timeframe of 90 days as of the end of the state of alert.

According to the points of view of various authorities, the building/demolition permits and town planning certificates remain valid throughout the state of alert and for an additional 90-day period after its termination, as they qualify as documents issued by public authorities and no special regulations have been issued in this respect. Moreover, this extension also applies to building/demolition permits for which the notice of commencement of works has been submitted.

However, one cannot ignore the annulment of some of the Government Decisions extending the state of alert. In one case, the Bucharest Court of Appeal issued the decision no. 1465/21 October 2021 according to which the annulment of the Government Decisions by which the state of alert was extended also triggers the retroactive removal of the state of alert declared thereby. However, the contentious administrative law provides that final court decisions annulling normative deeds have effects only for the future.

We emphasize that, although, apparently, the provisions of Law 55/2020 on the measures for preventing and combating the effects of the COVID-19 pandemic (by which the automatic prolongation of the validity of deeds issued by authorities was enacted) are meant to help investors, practice shows us that the application of this law may become problematic, especially in respect of town planning certificates, namely in respect of the building permitting procedure.

Thus, an investor with an urban planning certificate that expires during the state of alert will face a situation where he will only have an additional 90 days (calculated as of the end of the state of alert) to obtain all the necessary approvals for the building permit to be issued. Moreover, it is possible that the planning certificate will also require the preparation of a zoning plan (PUZ) or other planning documentation in order to obtain the building permit.

The experience has shown us that it is unlikely for the process of obtaining all the necessary approvals to be completed in 90 days, especially considering that there will be an increased number of applications to be submitted in the period following the expiry of the state of alert.

An expired town planning certificate at the end of the 90 days following the state of alert period, without having obtained a building permit, would trigger the obligation to a re-initiation of the entire authorization procedure. Moreover, the state of alert is usually extended for successive 30-day periods, yet the extension is carried out by default and there is no predictability as to when such an ("automatic") extension will no longer be decided by the Government. Consequently, an investor cannot assess the moment when the state of alert will end in order to be ready to start or complete, as the case may be, the obtaining of all necessary approvals or to apply for a formal extension of the urban planning certificate under Law 50/1991 on the authorization of construction works.

Thus, we have to balance two different regulations having the same purpose: on one hand, the specific regulation on authorizing the execution of construction works (Law 50/1991), which allows town planning certificates and building/demolition permits to be extended once for a period of up to 12 months and, on the other hand, the state of alert regulation which provides the automatic extension of the documents for the duration of the state of alert and for an additional period of 90 days after its termination.

What we would like to emphasize is that a formal extension by 12 months of town planning certificates and building / demolition permits gives predictability to the process of authorization and execution of construction works, while the automatic monthly extension, based on government decisions which “perpetuate" the state of alert, is uncertain and unpredictable for such a process.

Concluding, in order to allow investors to act with greater predictability during the authorization procedure, there needs to be a clear regulation allowing investors (who intend to continue the authorisation of construction projects during the state of alert) to opt for the formal extension of the documentation by 12 months, in accordance with the procedure established by Law 50/1991. The same rationale applies for the completion of execution works based on building/demolition permits which were already issued.

By Roxana Dudau, Associate Partner, Alexandra Siminiceanu, Managing Associate, and Miruna Coderie, Senior Associate, Bancila, Diaconu si Asociatii

Romanian Knowledge Partner

Țuca Zbârcea & Asociații is a full-service independent law firm, employing cross-disciplinary teams of lawyers, insolvency practitioners, tax consultants, IP counsellors, economists and staff members. It also operates a secondary law office in Cluj-Napoca (Romania), and has a ‘best-friend’ agreement with a leading law firm in the Republic of Moldova. In addition, thanks to the firm’s dedicated Foreign Desks, the team provides the full range of services to international investors seeking to gain a foothold or expand their existing operations in Romania. Since 2019, the firm and its tax arm are collaborating with Andersen Global in Romania.

Țuca Zbârcea & Asociaţii is providing legal services in every aspect of business, covering all major areas of practice: corporate and M&A; litigation and international arbitration; corporate tax; public procurement; TMT; employment; insurance; banking and finance; capital markets; competition; healthcare and pharmaceutical; energy and natural resources; environmental; intellectual property; real estate; regulatory legal services.