Domanski Zakrzewski Palinka has advised OGP Gaz-System S.A. on a project involving the creation of a new gas supply corridor on the European market.
According to DZP, “on January 9, 2020, Gaz-System executed a contract with the German company Europipe GmbH for the supply of pipes for the Polish section of the Baltic Pipe. The contract covers the supply of pipes for the construction of a 275 km long offshore section and a short onshore section leading to the receiving terminal. The pipes will be shielded with an appropriate protective coating. Under the contract, Europipe will also provide temporary storage for the pipes and transport to a receiving point indicated by the pipeline contractor, to be selected by Gaz-System in the first half of 2020 in a separate procurement procedure.”
The DZP team included Partners Pawel Grzejszczak, Julita Zimoch-Tucholka, Artur Nowak, and Katarzyna Kuzma, Counsel Wojciech Hartung, Senior Tax Manager Jan Czerwinski, and Associate Weronika Jedrzejewska.